Demolition Existing house.
New Construction for two story single house with ADU
Main: 5 Bedroom 4 Bathroom, 3,470 SQFT
ADU: 2 Bedroom, 2 Bathroom, 1,000 SQFT
Location: Mountain VIew, CA
ποΈ Project: New Construction for two story single house with ADU
π Location: Mountain VIew, CA
Β
Hello everyone! It’s time for progress update on the Franklin project.
πΈ Visual Update:
– Before
– The house before we start demolition.
8/12/2023
π¨ Next Phase: After the demolition is completed, our team will begin site preparation. This includes clearing debris, leveling the ground, and getting everything ready for the foundation work.
8/22/2023
ποΈ Compaction Success: Our skilled team has just completed the compaction process, ensuring that the ground beneath our project site is solid and stable. This is a vital step to support the foundation of our upcoming structures.
ποΈ Project Update: What’s on the Horizon After Compaction? π§
Β With the successful completion of our compaction process, let’s look ahead to the next phase of our project.
π’ Upcoming Phase: Our next priority is the pier rebar work. This phase involves meticulously reinforcing the piers to ensure they are sturdy and resilient.
Β
8/29/2023
ποΈ Project Update: Pier Rebar Process Underway! π§
9/6/2023
9/18/2023
ποΈ Project Update: What’s Next After Pier Rebar Inspection? π§
Β We’re now shifting our focus to the foundation pouring process. This vital step involves carefully pouring and curing the concrete foundation that will support our project’s structures.